GDOT: Interstate Lane Closure for the I-16 at I-95 Improvement Projects Through October 15

FYI for those traveling to and from Chatham

Weather permitting, Georgia Department of Transportation (Georgia DOT) construction partners will close interstate lanes at the locations below for the 16@95 Improvement Projects, which will widen I-16 and reconstruct the I-16/I-95 Interchange. The lane closures are necessary for widening activities for I-16 and bridge work at the I-16/I-516 Interchange.

Pro Roof GA
The Button - donate today!

NOTE: Detour information is shown in red.


Daytime Closures

Monday, October 10, through Saturday, October 15, 8 a.m. to 3 p.m.
Intermittent right and left lane closures at the following locations:

  • I-16 westbound from the I-16/I-516 Interchange (MP 164) to the I-16/I-95 Interchange (MP 157)

Monday, October 10, through Saturday, October 15, 9 a.m. to 4 p.m.
Intermittent right and left lane closures at the following locations:

  • I-16 eastbound from the I-16/I-95 Interchange (MP 157) to I-16/I-516 Interchange (MP 164)

Monday, October 10, through Saturday, October 15, 8 a.m. to 5 p.m.
Intermittent right and left lane closures at the following locations:

  • I-516 westbound at the I-16 Interchange from MP 5 to MP 6
  • I-516 eastbound at the I-16 Interchange from MP 6 to MP 5

Overnight Closures

Monday, October 10, through Saturday, October 15, 7 p.m. to 6 a.m.
Intermittent right and left lane closures at the following locations:

  • I-16 westbound from the I-16/I-516 Interchange (MP 164) to the I-16/I-95 Interchange (MP 157)
  • I-16 eastbound from the I-16/I-95 Interchange (MP 157) to the I-16/I-516 Interchange (MP 164)

Monday, October 10, through Saturday, October 15, 9 p.m. to 5 a.m.
Double lane closures at the following locations:

  • I-95 northbound @ I-16 overpass (MP 98 to MP 100)
  • I-95 southbound @ I-16 overpass (MP 101 to MP 98)

Overnight Closures and Detours

Tuesday, Oct. 11, 10 p.m. to 5 a.m. (nightly)

  • I-16 eastbound at the I-16/I-95 Interchange (Map)

Motorists traveling on I-16 eastbound should take the I-95 southbound ramp (Exit 157A) exit at SR 204 (Exit 94) turn left off the ramp, then turn left to access I-95 northbound, then take the I-16 eastbound ramp (Exit 99A).
 
Tuesday, October 11, 2022, 10 p.m. to 5 a.m. (Nightly)

  • I-95 southbound to I-16 eastbound ramp (Exit 99A) (Map)

Motorists traveling on I-95 southbound should continue past the I-16/ I-95 Interchange, exit at SR 204 (Exit 94) turn left off the ramp, then turn left to access I-95 northbound, then take the I-16 eastbound ramp.
 
Tuesday, October 11, 2022, 10 p.m. to 5 a.m. (Nightly)

  • I-16 eastbound to I-95 northbound ramp (Exit 157B) (Map)

Motorists traveling on I-16 eastbound should exit to I-95 southbound (exit 157A), exit at SR 204 (Exit 94) turn left off the ramp, then turn left to access I-95 northbound.


Long-Term Closure

June 2, 2022, through May 31, 2023

  • Tremont Road under I-16 (Map)

Note: Tremont Road will be open during holiday work restriction time frames.

  • Motorists traveling on Tremont Road north of I-16 should take Telfair Road northbound, turn right on West Gwinnett Street, turn right onto I-516 eastbound, then exit at Tremont Road (Exit 4).
  • Motorists traveling on Tremont Road south of I-16 should take I-516 westbound to West Gwinnett Street (Exit 6), turn left on West Gwinnett Street, then left on Telfair Road to access Tremont Road north of I-16.

 